Androscoggin Mill Data Center

JGT2 Redevelopment · Status uncertain

Former paper mill site proposed for redevelopment into a data center by Sentinel Data Centers LLC, a $550M plan that prompted Maine Gov. Mills to veto a statewide data-center moratorium (LD 307) specifically to protect it -- the veto held after the House failed to override it 72-65. In June 2026, Sentinel notified site owner JGT2 Redevelopment that it did not intend to move forward; the site is reportedly being shopped to other operators, so its future is unresolved.

Estimated water use

Estimate

No published facility capacity (MW) is available yet. No estimate is shown without a published figure.

Lifecycle timeline

Observed

Confirmed events only, each with its source.

  1. April 24, 2026

    Gov. Mills vetoes statewide data-center moratorium, citing the Jay project

    LD 307 would have banned data centers over 20MW until Nov 2027; Mills said she would have signed it if it exempted the Jay project.

    Source
  2. April 29, 2026

    Maine House fails to override the veto, 72-65

    Override needed a two-thirds majority in both chambers; the House vote fell short, so the moratorium did not become law.

    Source
  3. ~June 2026

    Sentinel Data Centers withdraws from the project

    Town manager Shiloh LaFreniere said Sentinel notified the site owner it did not intend to move forward; the developer is reportedly pursuing other operators.

    Source

Observed hydrologic data

Observed

From nearby USGS and NOAA monitoring stations, refreshed monthly. Dashed lines mark lifecycle milestones.

Groundwater level (ft below surface)

2 stations, overlaid

Precipitation (in)

NOAA Livermore Falls 3.7 SSW, ME (GHCND:US1MEAN0049) · monthly average

Regulatory records

Observed

Water permits and environmental compliance records from EPA ECHO.

JGT2 REDEVELOPMENT LLCJAY, ME

0 inspections on record · 0 formal enforcement actions · full ECHO report ↗

JGT2 REDEVELOPMENT LLC - JAYJAY, ME

0 inspections on record · 0 formal enforcement actions · full ECHO report ↗

Drawdown story

Assessment

Is the water table's behavior near this facility consistent with its estimated draw — and how strong is the evidence? A fixed rubric, recomputed monthly; every number below is stored with the inputs that produced it. Method: attribution-v1.

  1. 1 · Pathway

    This facility withdraws surface water — its estimated draw acts on a river or pond, not this local water table.

  2. 2 · Detectability

    Expected drawdown at the nearest monitored well could not be computed (no water-use estimate is available).

  3. 3 · Signal

    No monitored well within 2 miles of this facility — there is no near-field record to compare against controls.

No local withdrawal pathway — estimated draw does not reach this water table directly.

Attribution evidence score: withheld · as of 2026-07-22 · attribution-v1

Estimate inputs uncertainNo water-use estimate available
Pathway0/35
Detectability0/15
Temporal signal0/30
Robustness0/20