Smithfield, RI
Smithfield Data Center
Hanton City Investments LLC · Status uncertain · Douglas Pike
Proposed business park with a data center as anchor tenant, on several hundred acres of woodland off Douglas Pike, behind Fidelity Investments' corporate campus and across from Bryant University. Developer Hanton City Investments LLC filed its application on May 4, 2026 -- one day before Smithfield's Town Council voted 4-1 to ban data centers outright in every zoning district. Whether the filing is grandfathered ahead of the ban is expected to be settled in court.
Estimated water use
EstimateNo published facility capacity (MW) is available yet. No estimate is shown without a published figure.
Lifecycle timeline
ObservedConfirmed events only, each with its source.
May 4, 2026
Hanton City Investments files its application
SourceMay 5, 2026
Town Council votes 4-1 to ban data centers town-wide
The ordinance lists data centers as "not permitted" in every zoning district; whether Hanton City's filing, submitted one day earlier, is grandfathered is expected to be litigated.
Source
Observed hydrologic data
ObservedFrom nearby USGS and NOAA monitoring stations, refreshed monthly. Dashed lines mark lifecycle milestones.
Groundwater level (ft below surface)
3 stations, overlaid
Streamflow (cubic ft/sec)
USGS Woonasquatucket River at Centerdale, RI (01114500) · monthly average
Precipitation (in)
NOAA North Central State Airport, RI (GHCND:USW00064710) · monthly average
Regulatory records
ObservedWater permits and environmental compliance records from EPA ECHO.
No permit or compliance record from these sources currently matches this facility. Maine and Rhode Island permit lists are not yet among this site's tracked sources.
Drawdown story
AssessmentIs the water table's behavior near this facility consistent with its estimated draw — and how strong is the evidence? A fixed rubric, recomputed monthly; every number below is stored with the inputs that produced it. Method: attribution-v1.
1 · Pathway
The operator has not disclosed where this facility's water comes from. Until a source is published, the assessment is capped: an unclassified pathway can never raise the score.
2 · Detectability
Expected drawdown at the nearest monitored well could not be computed (no water-use estimate is available).
3 · Signal
No monitored well within 2 miles of this facility — there is no near-field record to compare against controls.
Facility not yet operating; baseline being recorded.
Attribution evidence score: withheld · as of 2026-07-22 · attribution-v1